Total Nguzo Kumi Projects
Priority Development ProjectsTotal Budget
Total InvestmentAvg. Budget per Project
Average costDepartments Involved
Cross-Directorates| # | Sub-County | Total | Completed | Ongoing | Not Started | Under Procurement | Stalled | Total Budget Estimate |
|---|---|---|---|---|---|---|---|---|
| 1 | Ainabkoi | 321 | 254 | 57 | 1 | 9 | 0 | KES 1,297,746,324 |
| 2 | Eldoret CBD | 281 | 259 | 8 | 12 | 1 | 1 | KES 5,066,386,714 |
| 3 | Kapseret | 443 | 368 | 47 | 19 | 9 | 0 | KES 669,575,024 |
| 4 | Kesses | 425 | 383 | 19 | 13 | 10 | 0 | KES 1,375,645,773 |
| 5 | Moiben | 675 | 611 | 18 | 21 | 25 | 0 | KES 2,062,467,449 |
| 6 | Soy | 861 | 721 | 88 | 12 | 39 | 1 | KES 1,736,269,275 |
| 7 | Turbo | 661 | 509 | 115 | 10 | 27 | 0 | KES 2,399,882,405 |
| # | Department | Total Projects | Completed | Completion Rate | Total Budget Estimate |
|---|---|---|---|---|---|
| 1 | Agriculture, Agribusiness, Livestock and Fisheries | 430 | 369 |
|
KES 5,351,306,609 |
| 2 | Education, Technical Training, Gender, Social Protection and Culture | 1612 | 1300 |
|
KES 1,740,837,602 |
| 3 | Finance and Economic Planning | 0 | 0 |
|
KES 0 |
| 4 | Health Services | 653 | 625 |
|
KES 1,921,474,972 |
| 5 | Lands, Physical Planning, Housing and Urban Development | 76 | 68 |
|
KES 2,570,604,425 |
| 6 | Public Service Management, Administration and Devolved Units | 26 | 21 |
|
KES 1,668,518,260 |
| 7 | Roads, Transport and Public Works | 70 | 57 |
|
KES 481,174,647 |
| 8 | Trade, Industrialization, Tourism, Co-operatives and Enterprise Development | 4 | 1 |
|
KES 9,000,000 |
| 9 | Water, Irrigation, Sanitation, Energy, Environment, Natural Resources and Climate Change | 749 | 620 |
|
KES 581,810,481 |
| 10 | Youth Affairs, Sports, ICT and Innovation | 47 | 44 |
|
KES 283,245,968 |